Abstract
The paper discusses the short term scheduling of Hydrothermal for Tanzania Electricity Supply Company (TANESCO) Power System. The problem is to determine on hourly interval the Hydro and Thermal generation. The scheduling keeps balance between production and consumption in a reliable and economical way during the study period. Linear programming (LP) mathematical model using MATL4B has been developed. The constraints are hydrological balance, thermal power plants limitations and load requirements. The result from LP solution gave low operation cost. Generation was mainly from hydro and all reservoirs elevation was high at the end ofplanning period.
Recommended Citation
Kyaruzi, A. (2004). SHORT-TERM SCHEDULING OF A HYDRO-THERMAL SYSTEM USING LINEAR PROGRAMMING TECHNIQUE. Tanzania Journal of Engineering and Technology (TJET), 27(2), 52-59. https://doi.org/https://doi.org/10.52339/tjet.v27i2.352